The tender saw significant oversubscription, with 171 applications submitted for a cumulative capacity of 2,724 MW against the 1,000 MW called for. The CRE selected 63 projects representing a capacity of 1,006 MW, at a weighted average price of €78.57/MWh. This price is a slight increase compared to the previous period (€77.08/MWh), but remains well below earlier price levels, attributed to sustained competition and a high number of renewal projects.
The deliberation also highlights several recommendations. The CRE invites administrations to re-examine constraints limiting turbine height, aiming to reduce project costs and facilitate renewal projects, while considering local acceptance issues. It also stresses the need for further analysis to understand why some parks undergo renewal before their end-of-life or without proposing increased power capacity.
The CRE notes that the actual increase in installed capacity for this 12th period amounts to 816 MW, thus meeting the PPE3 objective of 800 MW excluding renewals. However, it recommends counting only the additional capacity for renewal projects to ensure this target is met with certainty.